615-244-6800 tpotts@wtei.us

State of Tennessee

Location:
Nashville, Tennessee

Architect: 
Engineer: I.C. Thomasson

Contractor:  
Wolfe & Travis Electric

Contract Value:  
$4,472,000

This project consisted of replacement of main switchgear in (7) State Office Buildings in downtown Nashville Tennessee.

The Buildings are:

      1. Tennessee Tower
      2. Andrew Johnson Building
      3. Andrew Jackson Building
      4. Rachel Jackson Building
      5. Citizen Plaza
      6. James K Polk Building
      7. Davey Crockett Building

        The scope included replacement of:

      1. E. Unit Substations
      2. Medium Voltage S&C Switchgear
      3. Fused Disconnects in Eaton Switchboards
      4. Various Switchboard Breakers
      5. 5kV Feeder to the 28th Floor of Tennessee Tower

 

During this effort we also performed maintenance and tightening of all electrical mechanical connections throughout the buildings. The building all remained in operation each day. All outages were scheduled with NES and work performed between 6pm Friday to 6am Monday.

The project demanded extreme scheduling efforts. Each building had multiple departments and each had their own agenda and requirements including the Tennessee Performing Arts Center.

Each building had its own effort at coordinating and ensuring the existing switchgear was able to be removed and new installed inside the time frames which meant that temporary feeds and multiple outages were required at each location. A New Mechanical HVAC Unit was installed and ceilings repaired in the Andrew Johnson Building. A 28 story 500mcm 5kV secondary feeder was replaced in Tennessee Tower which required special cable reels with breaking systems to ensure safe drop pulls thru (7) pull boxes on different floors.

At the end of each outage a building wide verification of all systems and equipment was back in operation and ready for the next work day.

Wolfe & Travis being the “Prime Contractor” managed the project, created the schedules, planned the outage, coordinated the subcontractors and coordinated all utility efforts as well as perform the electrical work.